"Temirzhol zhondeu" is working at an accelerated pace on the overhaul of the highway of Republican significance Kaztalovka-Zhanibek 95-138 km

"Temirzhol zhondeu" is working at an accelerated pace on the overhaul of the highway of Republican significance Kaztalovka-Zhanibek 95-138 km

According to the plan for the month of June, the following volumes were completed:

• Arrangement of a temporary bypass road with a plan of 4.44 km, 3.6 km completed; the total volume since the beginning of the year is 9 km;

• Arrangement of subgrade under the plan for the month of June 4 km, 6 km have been completed to date, the total volume amounted to 11 km;

• The construction of an additional base layer of soil, reinforced with inorganic binders, out of the planned 3 km for the month of June, 4.16 km were completed, where the total volume since the beginning of the year is 5.96 km;

• Construction of crushed stone-sand cement mixture out of the planned 3 km for June, 3.7 km was completed, the total figure since the beginning of the year is 9.4 km; • Coarse-grained asphalt concrete mix of 3 km planned for June has been completed in 6.25 km, where the total mileage since the beginning of the year is 11 km.

Work is underway to install reinforced concrete culverts along the main road and to procure road building materials. "Temirzhol zhondeu" is actively working to fulfill the set plan!