Results of 9 months of 2021 for Temirzhol zhоndeu LLP

With the plan under the contract of 172.3 km, the fulfillment was 207.5 km (120%), Of these, the implementation of the PMS:

Track machine station Aktobe - 69.6 km
Track machine station Astana - 54.8 km
Track machine station Birlik - 48.3 km
Shar production site - 34.8 km
Ballasting was carried out with track crushed stone in the volume of 509 thousand m3.
We thank all of our field workers for their productive work and maximum return!

All set tasks and goals have been exceeded